Extension requests considered at the Second Review Conference (2RC) Part 1
Extension requests considered at the 2RC Part 1 were for States Parties with stockpile destruction and clearance deadlines in 2021 (and earlier, in exceptional cases). Documents related to extension requests were uploaded in accordance with the timeline defined in the Guidelines for CCM Article 3 and Article 4 Extension Requests adopted at the 8MSP. The extension requests were analysed using the Methodology adopted at the 9MSP.
Article 3: Stockpile Destruction
- Bulgaria
Bulgaria’s Extension Request and Statement of Work (6 April 2020)
Annex A, Annex B and Annex C
Analysis Group feedback (29 April 2020)
Answers to the Analysis Group (15 May 2020)
Update on implementation of extension request work plan (11 August 2020)
Update on implementation of extension request work plan (8 February 2021)
Update on implementation of extension request work plan: presentation text and slides (24 September 2021)
- Peru
Note Verbale – Peru’s Extension Request and Annex (en español) – English translation and Annex (2 April 2020)
Analysis Group feedback (29 April 2020)
Note Verbale – Peru’s Extension Request, updated version (en español) – English translation (2 June 2020)
Article 4: Clearance
- Bosnia and Herzegovina
Note Verbale – Bosnia and Herzegovina’s Extension Request (28 September 2020)
Annex 1, Annex 2 and Annex 3
Analysis Group feedback (1 October)
Bosnia and Herzegovina’s Extension Request, updated version (5 October 2020)
Annex 1, Annex 2 and Annex 3
Answers to Analysis Group (6 October 2020)
- Chile
Chile’s Extension Request (en español) – English translation (24 January 2020)
Analysis Group feedback (24 February 2020)
Note Verbale – Answers to the Analysis Group (en español) – English translation (1 April 2020)
Note Verbale – Answers to the Analysis Group (en español) – English translation (13 May 2020)
Note Verbale – Chile’s Revised Extension Request (en español) – English translation (10 July 2020)
- Lebanon
Lebanon’s Extension Request (12 December 2019)
Analysis Group feedback (22 January 2020)
Answers to the Analysis Group – Attachment (6 February)
Lebanon’s Extension Request, updated version (25 February 2020)